Scope of work

  • High-security military environment with restricted access and movement controls
  • Decommissioning works across 11 separate plant rooms
  • Retention and protection of existing operational plant and services
  • Complex site logistics and waste removal routes across a large operational estate
  • Use of telehandler operations to facilitate material movements and waste management
  • Careful sequencing to maintain programme and minimise disruption.

 

Outcome:

Works were successfully completed over a six-week programme, with all redundant plant and associated services removed safely and efficiently. The retained infrastructure remained protected and operational throughout, allowing future project phases to proceed as planned.

 